| Project | Client | Value | Scope | Quantities | Roles | Dates |
|---|---|---|---|---|---|---|
Axminster Frequency Enhancements |
Network Rail | £8.2 million | Yeovil to Exeter Frequency Enhan | Principal Contractor | Jul - Dec 2009 | |
Bunchrew Level Crossing Upgrade |
Network Rail | £140,000 | Upgrade of Level Crossing | Wig wags, track circuits, SPOSS | Principal Contractor | Sep 2009 - Jan 2010 |
Gospel Oak to Barking |
Atkins | £400,000 | Signalling Upgrade & Enhancement | 36 locs, 1 REB, new signals etc | Signalling Sub-Contractor | Jul - Dec 2009 |
| Strathclyde DOO CCTV | Thales Rail Signalling Solutions | £64,500 | Design, production of test plan, existing location case modifications, recoveries | 18 location areas | Sub Contractor | Aug 08 - Dec 08 |
| Lugton | Jarvis | £50,000 | Build and supply of location cases and lamp fittings | 27 locs | Sub Contractor | Jan 09 - May 09 |
| Gospel Oak to Barking - Design | Jacobs | £600,000 | Detailed design of signalling works for the Gospel Oak to Barking Infrastructure Project | 41 locs, 1 REB, 1 NX Panel | Sub Contractor | Sep 08 - May 10 |
| Gospel Oak to Barking - Build | Jacobs | £400,000 | Manufacture, supply and 3A test of location cases and relocatable equipment buildings for the Gospel Oak to Barking Infrastructure Project | 36 locs, 1 REB | Sub Contractor | Apr 09 - Nov 09 |
| Milton Keynes | Signalling Solutions Ltd | £1,000,000 | Design, construct and 3A test of 40 location cases and 4 REB's for re-signalling project. | 40 locs, 4 REBs | Sub Contractor | Oct 07 - Dec 08 |
| Colchester - Clacton | Signalling Solutions Ltd | £1,500,000 | Design and construction of location cases and REB's for re-signalling project. | 232 locs, 5 REBs | Sub Contractor | Apr 07 - Jul 08 |
| JNUP | Tubelines | £1,500,000 | Supply of testing resource and installation resource and associated management. | 35 testers | Sub Contractor | Sep 08 - May 09 |
| WRCM - TV4 | Network Rail | £6,500,000 | Construction and testing of location cases for enabling works and final re-signalling. Production of specifications, location area plans, bonding records. Project engineering assistance, signal sighting, site assurance, source record management. Enabling works core design. | 356 Locs, 7 REBs, 17 A/C Diss Box | Sub Contractor | Nov 05 - May 10 |
| WCRM - Rugby Station | Network Rail | £432,900 | Construction test and supply of enabling works location cases and provision of construction management and installation resources. | 38 locs, 220 Power enclosures | Sub Contractor | Sep 06 - Sep 08 |
| Wemyss Bay Location Cases | Network Rail | £118,000 | Design, factory test and supply of location cases, provision of construction management and installation resources. | 7 location cases | Sub Contractor | Apr 08 - May 08 |
| WCRM - South Manchester | Ansaldo Segnalamento Ferroviario (ASF) | £477,000 | Internal fit out of 32 Computer Based Interlocking (CBI) Equipment Buildings, Systems Integration, Provision of engineering support to adapt CBI to Network Rail Standards. | 32 CBI Equipment Buildings | Sub Contractor | Aug 04 - Mar 05 |
| Docklands Light Railway Racks | Thales Rail Signalling Solutions | £400,000 | Construction and factory test of relay racks for Docklands Light Railway. Site modification and test. | 12 free standing equipment racks | Sub Contractor | Feb 06 - Aug 09 |
| Amsterdam Utrecht | Bombardier Transportation | £160,000 | Provision of engineering support by IRSE licensed designers, installation resources and site management personnel. | 5 Relay Houses | Sub Contractor | Sep 04 - May 06 |